![]() It transpired in this case that after the architect issued the completion certificate under the SIA Conditions, GTH Engineering & Construction Pte Ltd (GTH) served a final payment claim in the form of a "payment claim 16B", only to subsequently serve yet another payment claim, in the form of a "payment claim 17". ![]() The SIA Conditions 2005 provided that a payment claim can be made at any time before a final payment claim, but was silent as to whether a further payment claim could be made after submission of the final payment claim. In Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd 4 SLR 615, the contract in question was based on the Singapore Institute of Architects' Articles and Conditions of Building Contract (Lump Sum Contract) (7th Ed, April 2005) (SIA Conditions 2005).